  I. the inspection before the commissioning of the fuel engine has three aspects:pmJBoiler Burner

  1. Check whether the diesel is in place, whether the fuel line is clean and unobstructed, and whether the valve has been opened.pmJBoiler Burner

  2. Whether there is pipeline leakage phenomenon and whether the pipeline installation is reasonable.pmJBoiler Burner

  3. Whether the oil inlet and return pipe is installed correctly, and the return pipe is not allowed to install the valvepmJBoiler Burner

  Two, fuel engine internal inspectionpmJBoiler Burner

  1. Whether the nozzle of the burner is installed and the ignition electrode is properly adjusted.pmJBoiler Burner

  2. Whether the rotation direction of the motor is correct.pmJBoiler Burner

  3. Whether the external circuit connection meets the requirements.pmJBoiler Burner

  4. Perform cold state simulation of the combustion machine according to the line condition, and observe whether all parts of the equipment are normal in operation and whether the flame detection and protection part is normal.pmJBoiler Burner

  Third, the combustion engine debuggingpmJBoiler Burner

  1. Check whether the external diesel is in place, whether the pipeline is unobstructed and the external power supply is in place.pmJBoiler Burner

  2. Adjust the load of the burner to a small load and the ignition position to a small load accordingly. Turn off the large load for ignition and observe the flame condition.pmJBoiler Burner

  3. Adjust the fire output of the combustion machine, according to the load of the thermal equipment, from a relatively small load to a large load adjustment, and according to the situation of the servo motor or throttle adjustment.pmJBoiler Burner

  4. Observe the unbiased flame, incomplete flame combustion, vibration and other phenomena.pmJBoiler Burner

  5. Conduct multiple ignition after adjustment to observe whether the ignition is good.pmJBoiler Burner

  Iv. Site requirements:pmJBoiler Burner

  1. Personnel irrelevant to debugging operation shall leave the operation site.pmJBoiler Burner

  2. Any other operation (such as welding, gas cutting, etc.) is prohibited.pmJBoiler Burner

  3. In order to ensure the personal safety of the debugging personnel, when the burner is ignited, it should be 1 meter away from the side of the burner. When the flame is stable, it can observe the flame in the observation mirror and make the next output adjustment and other adjustments.pmJBoiler Burner

  Five, fuel engine debugging and maintenance matters needing attentionpmJBoiler Burner

  1. In case of continuous failure of the secondary ignition program of the fuel burner, it shall stop the machine to check whether the fuel supply system of the burner is normal and whether the circuit connection is correct. Only after the fault is solved can the burner be restarted.pmJBoiler Burner

  2. Smoking, welding, cutting and other illegal operations are strictly prohibited.pmJBoiler Burner

  3. During debugging, it is necessary to be serious, safe and efficient.pmJBoiler Burner

  4. No explosion-proof electric power tools are allowed on site.pmJBoiler Burner

  5. Explain safety operation precautions to customers in detail.pmJBoiler Burner

  6. Check whether the oil circuit is open before starting up.pmJBoiler Burner

  7. It is suggested that the commissioning of fuel engines should not be carried out at night.pmJBoiler Burner

  8. At the end of debugging, operators should be organized to train them on the direction of operation and establish operation procedures if necessarypmJBoiler Burner